This is the fifth Interim Report of the Indonesia Domestic Biogas Programme (IDBP) which has been running since 15 May 2009. The implementation of IDBP this year is funded by the Royal Norwegian Embassy and ENDEV, and implemented by Hivos and Yayasan Rumah Energi with assistance from SNV, which started on 1 January 2014 and will run under the current contribution agreement until 31 December 2014. This Interim Report 2014 describes the activity undertaken from 1 January 2014 until 30 June 2014 in anticipation of the National Biogas Advisory Committee meeting in September 2014.
The funding for the Indonesia Domestic Biogas Programme by the Royal Norwegian Embassy is allocated for the activities in seven provinces: East Java, Central Java (including Yogyakarta), West Java, Nusa Tenggara Barat, Nusa Tenggara Timur, South Sulawesi and Lampung and scheduled to finish by 31 December 2014. Activities in the provinces in Java are also funded by GIZís ENDEV Programme and government matching funds for subsidies.
Under this funding agreement, 989 (out of the targeted 4,000 units, 25%) biogas digesters have been built from January-June 2014. Hivos contributes through the carbon credit funds obtained by IDBP through the carbon mechanism which is registered under the Gold Standard.
Please click the here to download the Interim Report. If the link does not work, please request by e-mail to [email protected]